Prerequisites
-
Before you perform any procedures, review the safety guidelines in the Cisco Network Convergence System 6000 Series Routers Hardware Installation Guide to avoid injuring yourself or damaging the equipment.
-
Before cabling the system, install each chassis in the planned location. Ensure that you have adequate floor space to cable the multi-chassis configuration and an environment that meets the recommended specifications. For more information, see the Cisco Network Convergence System 6000 Series Routers Site Planning Guide.
-
Perform the Router Health check on the router to ensure that any errors or exception are resolved prior to migrating to 2T multi-chassis mode. See Commands for Router Health Check.
-
Verify that the LCC and FCC are running Cisco IOS XR release 6.3.2 or later (with all applicable SMUs and packages).
-
Install NC6-FANTRAY-2 Fan Trays in the LCC. See the Replacing the Fan Tray section in the Cisco Network Convergence System 6000 Series Routers Hardware Installation Guide.
-
Verify that field-programmable device (FPD) upgrades are completed for all FPDs on both routers by using the show hw-module fpd command. For any FPD components that show status as NEED UPGD, use the upgrade hw-module location location fpd command. For any FPD components that show status as RLOAD REQ, use the hw-module location location reload command.
-
Create a backup of the running configuration using the copy running-config command in both System Admin EXEC mode and XR EXEC mode.