Upgrade C-Band to C+L Band Without Affecting Traffic Flow
Feature Name |
Release Information |
Description |
---|---|---|
Nontraffic Affecting C+L Band Upgrade |
Cisco IOS XR Release 7.10.1 |
Upgrading an existing C-band network to a C+L band network is now possible without impacting the traffic flow. Cisco Optical Network Planner (CONP) computes the values for relevant parameters in C+L network configuration. The upgrade benefits even those networks that were not planned for a future L-band upgrade. C+L band upgrade enables you to accommodate more bands to your network to boost network bandwidth. |
Perform the following procedure to bring up the L-band node while upgrading a C-band only network to a C+L network.
Note |
Use the Cisco Optical Network Planner (CONP) to compute the following values for C-band and L-band devices in C+L network configuration:
|
Procedure
Step 1 |
Configure proper gain and gain-range on all L-band nodes.
The following is a sample configuration that disables Gain Estimator.
|
||
Step 2 |
Configure Single band PSD on all L-band nodes.
The following is a sample configuration that disables Link Tuner.
|
||
Step 3 |
Configure Dual band configuration (dual band PSD set points that are obtained from CONP and partner-band configuration) values on all L-band nodes. For more information on L-Band dual band PSD configuration, see Modify L-Band Amplifier Properties. |
||
Step 4 |
Configure proper gain and gain-range computed by gain-estimator application manually on all C-band nodes and then disable gain-estimator.
|
||
Step 5 |
Configure single band PSD set points that are obtained from Link Tuner manually on all C-band nodes and disable Link Tuner.
|
||
Step 6 |
Configure dual band configuration (dual band PSD configuration set points that are obtained from CONP and partner-band configuration) values on all C-band nodes. For more information on C-Band dual band PSD configuration, see Modify C-Band Amplifier Properties
|
||
Step 7 |
Bring up the Interlink connectivity between C-band and L-band devices by enabling the management interfaces for partner-band communication between C-band and L-band nodes. |
||
Step 8 |
Bring up the fiber connectivity between C-band and L-band devices and enable Gigabit Ethernet interfaces.
|
||
Step 9 |
Verify that the connectivity is fine and there are no alarms present on OSC and OTS controller. |
||
Step 10 |
After the connectivity is completed till the last terminal node, verify that the topology is UP, and APC cleared the PARTIAL TOPOLOGY alarm on all OLT C-band and L-band nodes. The following sample is an output of show olc apc command.
|
||
Step 11 |
On the L-band bfr manager, band status remains NA until end-to-end connectivity is up. After end-to-end terminal (OLT-OLT) is discovered, band status populates all the agent nodes. BFR initiates the BRING UP (RECOVERY) procedure and recovers one node at a time. The following example shows the output of the show olc band-status command where the L-Band recovery is not initiated and BFR status is NA.
The following example shows the output of the show olc band-status command where the L-Band recovery is in progress and BFR status is Running.
|
||
Step 12 |
Wait for the recovery to complete on all nodes. When recovery completes, check the PSD status of the C-band and partner L-band nodes, and verify that the PSD profile is DUAL BAND PSD. |
||
Step 13 |
Verify that BFR converged on all nodes and the state on the agent nodes are ACTIVE with DUAL BAND PSD. The following example shows the output of the show olc band-status command where the L-Band bring up is complete, PSD profile is DUAL BAND PSD, and band status of all agent nodes is Active.
|
||
Step 14 |
Check the traffic status on C-band nodes and verify that traffic was not impacted during L-band addition. |