Installing a Half-width Blade Server
Before you begin
The blade server must have its cover installed before installing the server into the chassis to ensure adequate airflow.
Procedure
Step 1 |
Grasp the front of the blade server and place your other hand under the blade to support it. |
Step 2 |
Open the ejector levers in the front of the blade server. |
Step 3 |
Gently slide the blade into the opening until you cannot push it any farther. |
Step 4 |
Press the ejector so that it catches the edge of the chassis and presses the blade server all the way in. |
Step 5 |
Tighten the captive screw on the front of the blade to no more than 3 in-lbs. Tightening only with bare fingers is unlikely to lead to stripped or damaged captive screws. Cisco UCS Manager automatically reacknowledges, reassociates, and recommissions the server, provided any hardware changes are allowed by the service profile. |