This appendix contains a sample preliminary site survey that you should complete before planning a detailed site survey. This preliminary survey ensures that the basic system requirements have been completed or are underway before detailed site plans are completed.
Preliminary Site Survey
This table shows a sample preliminary site survey form.
Preliminary Site Survey |
|
---|---|
Order Information | |
Sales order number |
|
Estimated shipping date |
|
Site ready date |
|
Installation date |
|
Site Location and Address |
|
Company name |
|
Site address |
|
Shipping address |
|
Building or computer room access |
|
Special instructions |
|
Hours and days of operation |
|
Primary Contact |
|
Name |
|
Title |
|
Phone number |
|
Mobile phone number |
|
Fax number |
|
Pager number |
|
Email address |
|
Secondary Contact |
|
Name |
|
Title |
|
Phone number |
|
Mobile phone number |
|
Fax number |
|
Pager number |
|
Email address |
|
Delivery and Installation Constraints |
|
Is there a loading dock available to unload the equipment at this site? |
|
Is the path to the installation area unobstructed? If not, can special arrangements be made to get the equipment to the installation area? Describe them. |
|
On what floor is the installation? |
|
If it is on a floor other than the ground floor, is there a freight elevator available? Note whether the equipment will have to be brought up a flight of stairs. |
|
Is there someone on site during working hours to accept delivery of the materials? If not, list the times this person would be available. |
|
Floor Mounting |
|
How many chassis will be installed? Is there floor space available for all of the chassis? |
|
Make a sketch of the area where the chassis is to be installed and note the chassis location. |
|
Power |
|
Is AC or DC power available for the chassis? How much power is required? Is there a connection point on the panel for the chassis? |
|
Is there a fuse access panel (FAP) available for the equipment? Provide a connection point on the FAP for each chassis. |
|
Will a fuse access panel be installed in time for the routing system installation? Provide a date when the FAP will be installed. |
|
Is the FAP in the same room as the chassis? |
|
Is there an AC power outlet (220 V or 110 V) located within 10 feet of each chassis for PCs and test equipment? |
|
Is there proper grounding for the equipment? If not, when will the grounding be available? Provide a connection point for the grounding. |
|
Are there any restrictions when the equipment can be powered on or when electrical work can be done? If so, describe them. |
|
Are there special requirements for power or power cables (for example, a different wire gauge)? If so, describe them. |
|
Air Conditioning |
|
Does the site have the air conditioning capacity to handle the routing system? If not, note what will be done to rectify the lack of adequate cooling. |
|
Describe the air conditioning at the site. |
|
Cable Plant |
|
Have the cables been pulled for all data interfaces? If not, list the outstanding cabling that needs to be installed and the scheduled completion dates. |
|
Are there connection points on the fiber distribution panel for all optical cables connecting to the routing system? |
|
Will fiber jumpers be provided? What length of fiber jumper is required to complete the installation? |
|
What type of fiber connector is used at the site? |
|
If attenuation is required, will attenuators be provided? |