NTP-L38 Performing the NCS 2002 Shelf Installation Acceptance Test
Purpose |
Use this procedure to perform a shelf installation acceptance test for the NCS 2002. |
Tools/Equipment |
Voltmeter |
Prerequisite Procedures |
None |
Required/As Needed |
Required |
Onsite/Remote |
Onsite |
Security Level |
None |
Procedure
Step 1 |
If you installed an NCS 2002 shelf, verify each applicable procedure that was completed.
|
||||||||||||||||||
Step 2 |
Complete the DLP-L49 Connecting Office Power (AC) to the NCS 2002 Shelf. |
||||||||||||||||||
Step 3 |
Complete the DLP-L61 Measuring DC Voltage on the NCS 2002 Shelf. |
||||||||||||||||||
Step 4 |
Continue with Connect the PC and Log into the GUI. Stop. You have completed this procedure. |
DLP-L60 Inspecting the NCS 2002 Shelf Installation and Connections
Purpose |
Use this task to inspect the shelf installation and connections and verify that everything is installed and connected properly. |
Tools/Equipment |
None |
Prerequisite Procedures |
None |
Required/As Needed |
Required |
Onsite/Remote |
Onsite |
Security Level |
None |
Procedure
Step 1 |
Make sure all external wiring connections (that is, power, ground, alarms, and so on) are secure. If a wire or cable is loose, return to the appropriate procedure in this chapter to correct it. |
Step 2 |
Return to your originating procedure (NTP). |
DLP-L61 Measuring DC Voltage on the NCS 2002 Shelf
Purpose |
Use this task to measure the power to verify correct power and returns. |
Tools/Equipment |
Voltmeter |
Prerequisite Procedures |
Before installing the DC power, check the voltage |
Required/As Needed |
Required |
Onsite/Remote |
Onsite |
Security Level |
None |
Caution |
Do not apply power to the shelf until you complete all the installation steps. |
Warning |
To ensure safety of personnel and equipment, do not connect any power cables into the power module until the module is completely installed into the chassis. Statement 389 |
Warning |
To reduce the risk of electric shock, switch on the power only after the power cord is completely installed into the power module. Statement 390 |
Procedure
Step 1 |
Using a voltmeter, verify the office ground and power:
|
Step 2 |
Using a voltmeter, verify the shelf ground and power wiring: |
Step 3 |
Repeat Steps 1 and 2 for the RET2 (B) and -48V (B) of the redundant power supply input. |
Step 4 |
Return to your originating procedure (NTP). |